Step 1. Preparation
- Secure Permits: Obtain an Electrical Permit from the Office of the Building Official (OBO).
- Gather additional requirements [ View complete requirements ]
-
Hire an Electrical Practitioner: Engage an accredited electrician or electrical practitioner to handle your metering setup.
- Click here for the list of accredited electrician and types of metering set up.
Step 2. Endorsement
-
Formally submit and endorse your application through your hired Electrical Practitioner
Step 3. Site Survey
-
Our team will conduct a survey to inspect the metering set up within 2 to 3 working days after endorsement.
Step 4. Payment, Agreement & Documents Submission
Pay Required Deposit: Once the inspection is approved, update your bill deposit based on the inspection result at any authorized payment or service center.
-
Sign Contract: Sign your new Electric Service Agreement at any of our Service Center near you.
Step 5. Installation and Energization
-
Final Setup: Meter installation and energization typically take 2 to 3 working days after signing of agreement.
Note: Applications that require additional power line work or have a load requirement above 8,000 watts may take 10–15 working days for service connection, depending on the scope of work required.